Things are looking up for GCP’s production times. There is a decrease in times for Premlene Sheet Rubber, Premlene Eng. Structures, and GCP Clamps/Fittings. National Silicone Solid, GCP Hose, and GCP UHMW-PE Sheet continue to stay the same. You may notice that our National Silicone line has been split into two parts, Solid and Sponge. This is because there is approximately a 15 day difference between the two, which we felt was enough to have them separated.
August 2020 – Current Times
Premlene Sheet Rubber: 35-40 Days
Premlene Eng. Structures: 55-60 Days
National Silicone Solid: 35-40 Days
National Silicone Sponge: 20-25 Days
GCP Hose: 50-55 Days
GCP Clamps/Fittings: 55-60 Days
GCP UHMW-PE Sheet: 60-65 Days
July 2020 – Last Month
Premlene Sheet Rubber: 40-45 Days
Premlene Eng. Structures: 60-65 Days
National Silicone: 35-40 Days
GCP Hose: 50-55 Days
GCP Clamps/Fittings: 60-65 Days
GCP UHMW-PE Sheet: 60-65 Days