Our product lines have seen a slight improvement in overall average production time, now averaging 50.3 days, which represents a reduction of one day. Notably, this improvement was driven by the Premlene Engineered Structures line, which experienced a 10-day reduction. In contrast, all other product lines remained unchanged.
The improvement in production time for the Premlene Engineered Structures line can be attributed to an increase in production capacity. As noted in our previous month’s report, manufacturing lead times have remained relatively consistent and are projected to stay that way through August. The consistent lead times can be attributed to a couple of factors including decreased domestic demand and uninterrupted access to input/processing materials.
GCP Sourced Hose
Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.
August Production Times
Our August 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container. However, it excludes ocean shipping and other transit times.
If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.
Premlene
– Sheet Rubber: 40-45 Days
– Eng. Structures: 55-60 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 40-45 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Molded Parts: 55-60
– Clamps/Fittings: 55-60 Days
– UHMW-PE Sheet: 50-55 Days
Premlene
– Sheet Rubber: 40-45 Days
– Eng. Structures: 65-70 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 40-45 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Molded Parts: 55-60
– Clamps/Fittings: 55-60 Days
– UHMW-PE Sheet: 50-55 Days