This month, there have been no changes in production times compared to the previous month, with the average duration for completing orders remaining stable at 59.5 days. A key factor in maintaining these consistent production times is the Chinese New Year holiday, which significantly impacts manufacturing activities across China. This annual holiday results in temporary factory shutdowns as workers return to their hometowns for celebrations. Operations are expected to resume fully by February 20th.
The wider economic context shows that China’s manufacturing sector continues to face challenges, but is showing some signs of life. China’s manufacturing Purchasing Managers Index (PMI) unexpectedly reported a 50.8 in January 2024, the same as December’s figure but above market forecasts of 50.6. It was the third straight month of growth in factory activity, along with foreign sales growing for the first time in 7 months.
GCP Sourced Hose
Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.
February Production Times
Our February 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container, which currently stands at an average of 10.5 days. However, it excludes ocean shipping and other transit times.
Approximate transit times (including estimated time the ship will wait at the port before it is unloaded) are:
East Coast: 35-45 days
West Coast: 20-30 days
If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.
Premlene
– Sheet Rubber: 50-55 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 55-60 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 65-70 Days
GCP Sourced
– Molded Parts: 65-70 Days
– Clamps/Fittings: 60-65 Days
– UHMW-PE Sheet: 60-65 Days
Premlene
– Sheet Rubber: 50-55 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 55-60 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 65-70 Days
GCP Sourced
– Molded Parts: 65-70 Days
– Clamps/Fittings: 60-65 Days
– UHMW-PE Sheet: 60-65 Days