January 2020 Production Times

Rolls of cloth inserted black SBR rubber - GCP Industrial Products
Rolls of cloth inserted black SBR rubber - GCP Industrial Products

Overall, January’s production times have continued to stay positive. Premlene, National Silicone, and GCP Ceramic Tile do show a slight increase in production times. While GCP UHMW-PE production time have decreased. Premlene Eng. Structures, GCP Conveyor Belt, and GCP Clamps/Fittings production times stay the same. 

January 2020 – Current Times

Premlene Sheet Rubber: 50-55 Days

Premlene Eng. Structures: 60-65 Days

National Silicone: 40-45 Days

GCP Ceramic Tile: 50-55 Days

GCP Conveyor Belt: 60-65 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 55-60 Days

GCP UHMW-PE Sheet: 60-65 Days

December 2019 – Last Month

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 60-65 Days

National Silicone: 35-40 Days

GCP Ceramic Tile: 40-45 Days

GCP Conveyor Belt: 60-65 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 55-60 Days

GCP UHMW-PE Sheet: 65-70 Days

 