Overall, January’s production times have continued to stay positive. Premlene, National Silicone, and GCP Ceramic Tile do show a slight increase in production times. While GCP UHMW-PE production time have decreased. Premlene Eng. Structures, GCP Conveyor Belt, and GCP Clamps/Fittings production times stay the same.
January 2020 – Current Times
Premlene Sheet Rubber: 50-55 Days
Premlene Eng. Structures: 60-65 Days
National Silicone: 40-45 Days
GCP Ceramic Tile: 50-55 Days
GCP Conveyor Belt: 60-65 Days
GCP Hose: 50-55 Days
GCP Clamps/Fittings: 55-60 Days
GCP UHMW-PE Sheet: 60-65 Days
December 2019 – Last Month
Premlene Sheet Rubber: 40-45 Days
Premlene Eng. Structures: 60-65 Days
National Silicone: 35-40 Days
GCP Ceramic Tile: 40-45 Days
GCP Conveyor Belt: 60-65 Days
GCP Hose: 50-55 Days
GCP Clamps/Fittings: 55-60 Days
GCP UHMW-PE Sheet: 65-70 Days