The average expected production time for all GCP products in January is around 75 days. Increasing 3.5 days from December.
For the most part, expected production times held steady from December into the New Year. Premlene Sheet rubber and GCP UHMW PE sheet production both increased by 5 days, though, National Silicone Foam shows a decrease in production time by 5 days. GCP Sourced Clamps/Fittings saw the largest jump at plus 20 days. The factors which caused the increase include the upcoming Chinese New Year celebrations and Olympic games shutdowns, as well as the factory continuing to run at full capacity due to elevated demand.
Molded Parts
With respect to our molded parts, this is the fifth month in a row which we did not publish a production number. We continue experience a wide variation of times depending on the style needed. If you are looking to submit an order for our molded parts please contact us to find out the appropriate lead times.
January Production Times
Our January 2022 production times measure the change in days an average order will take to produce from time it is submitted (all facilities). This includes the time it takes to book a container. However, it excludes ocean shipping and other transit times.
If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.
Premlene
– Sheet Rubber: 80-85 Days
– Eng. Structures: 70-75 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 45-50 Days
– Foam: 70-75 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Hose: 80-85 Days
– Molded Parts: Contact Us
– Clamps/Fittings: 105-110 Days
– UHMW-PE Sheet: 80-85 Days
Premlene
– Sheet Rubber: 75-80 Days
– Eng. Structures: 70-75 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 45-50 Days
– Foam: 65-70 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Hose: 80-85 Days
– Molded Parts: Contact Us
– Clamps/Fittings: 85-90 Days
– UHMW-PE Sheet: 75-80 Days