This month, we’ve observed a large increase in the production timelines for our products. The current average duration for completing orders has reached 59.5 days, marking a rise of 10 days from the previous 49.5. Specifically, our Premlene Sheet Rubber and National Silicone Solid product lines both experienced a 15-day extension in production time. The production period for National Silicone Sponge has expanded by 20-days. Additionally, there’s a 5-day increase in the production time for our Engineered Structures line and GCP Sourced Clamps/Fittings, while GCP Sourced Molded, UHMW-PE Sheet parts, and National Silicone Foam have seen a 10-day increase. The production times for all other product lines have remained consistent.
Contributing to these increases are the forthcoming Chinese New Year celebrations, which begin in February, and weakened demand continues to impact factory operations, by way of reduced staffing and shuttered capacity to decrease costs. In Presidents Xi Jinping’s New Year’s Eve address, he mentioned China’s businesses are struggling and job seekers have trouble finding work.This is the first time Xi has mentioned economic challenges in his annual New Year’s messages since he started giving them in 2013. The country’s massive manufacturing sector had been weak for most of 2023. After a brief pickup in economic activity in the first quarter of last year, the official manufacturing PMI contracted for five months until September. Then it dipped below 50 again.
GCP Sourced Hose
Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.
January Production Times
Our January 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container, which currently stands at an average of 10.5 days. However, it excludes ocean shipping and other transit times.
Approximate transit times (including estimated time the ship will wait at the port before it is unloaded) are:
East Coast: 35-45 days
West Coast: 20-30 days
If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.
Premlene
– Sheet Rubber: 50-55 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 55-60 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 65-70 Days
GCP Sourced
– Molded Parts: 65-70 Days
– Clamps/Fittings: 60-65 Days
– UHMW-PE Sheet: 60-65 Days
Premlene
– Sheet Rubber: 35-40 Days
– Eng. Structures: 55-60 Days
National Silicone
– Solid: 40-45 Days
– Sponge: -35-40 Days
– Foam: 35-40 Days
Rubatex
– Sponge: 65-70 Days
GCP Sourced
– Molded Parts: 55-60 Days
– Clamps/Fittings: 55-60 Days
– UHMW-PE Sheet: 50-55 Days