June 2023 Production Times

The process of rolling rubber
The process of rolling rubber

There has been no alteration in the average production time across our entire product range compared to last month, keeping the overall average at 52.5 days. However, the Premlene Engineered Structure line observed an extension of 5 days, whereas the GCP Molded Parts lines witnessed a reduction of 5 days. The production times for all other product lines remained unaffected.

China’s manufacturing industry is clearly positioned to adapt and react to changing market demands. A recent private sector survey revealed an unexpected growth in China’s factory activity during May, reversing the previous decline. This positive shift can be attributed to lower input costs, enhanced production levels and higher demand, providing relief to struggling factories that have been impacted by the fragile and uneven recovery from China’s past strict COVID curbs.
 

GCP Sourced Hose

Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.

June Production Times

Our June 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container. However, it excludes ocean shipping and other transit times.

If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.

 

June 2023 Production Times:
Premlene
– Sheet Rubber:  45-50 Days
– Eng. Structures: 65-70 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 70-75 Days

GCP Sourced
– Molded Parts: 55-60
– Clamps/Fittings: 55-60  Days
– UHMW-PE Sheet: 50-55 Days
May 2023 Production Times:
Premlene
– Sheet Rubber:  45-50 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 70-75 Days

GCP Sourced
– Molded Parts: 60-65
– Clamps/Fittings: 55-60  Days
– UHMW-PE Sheet: 50-55 Days