There has been no alteration in the average production time across our entire product range compared to last month, keeping the overall average at 52.5 days. However, the Premlene Engineered Structure line observed an extension of 5 days, whereas the GCP Molded Parts lines witnessed a reduction of 5 days. The production times for all other product lines remained unaffected.
GCP Sourced Hose
Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.
June Production Times
Our June 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container. However, it excludes ocean shipping and other transit times.
If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.
Premlene
– Sheet Rubber: 45-50 Days
– Eng. Structures: 65-70 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Molded Parts: 55-60
– Clamps/Fittings: 55-60 Days
– UHMW-PE Sheet: 50-55 Days
Premlene
– Sheet Rubber: 45-50 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Molded Parts: 60-65
– Clamps/Fittings: 55-60 Days
– UHMW-PE Sheet: 50-55 Days