Our May 2021 production times measure the change in days an average order will take to produce from time it is submitted (all facilities), this includes the time it takes to book a container. However, it excludes ocean shipping and other transit times. Meaning, the lower the number the quicker we expect to produce an order and have it ready to ship.
The average expected production time for all GCP products in May is 71 days. Up 2 days from April.
Overall lead times increased again this month as our production partners continue to struggle with managing demand and capacity in the face of chronic logistics and labor issues.
Extended lead times, wide-scale shortages of basic materials, rising commodities prices and difficulties in transporting products are affecting all segments of the manufacturing economy.
Please be assured we are doing what we can to produce and ship all orders on time. We encourage all customers to order as early as they can to avoid potential inventory shortages or stock outs. We anticipate demand to remain high and longer than normal shipping times to continue for the foreseeable future.
If you have any concerns with your orders on hand or about future orders please contact us for additional support.
Premlene Sheet Rubber: 60-65 Days
Premlene Eng. Structures: 80-85 Days
National Silicone Solid: 55-60 Days
National Silicone Sponge: 55-60 Days
GCP Hose: 80-85 Days
GCP Molded Parts: 60-65 Days
GCP Clamps/Fittings: 80-85 Days
GCP UHMW-PE Sheet: 80-85 Days
Premlene Sheet Rubber: 65-70 Days
Premlene Eng. Structures: 80-85 Days
National Silicone Solid: 55-60 Days
National Silicone Sponge: 40-45 Days
GCP Hose: 80-85 Days
GCP Molded Parts: 65-70 Days
GCP Clamps/Fittings: 75-80 Days
GCP UHMW-PE Sheet: 70-75 Days