Expected production times increased slightly heading into May as 87 of China’s 100 largest cities by GDP have imposed some form of quarantine curbs in an effort to enforce its zero-Covid strategy. Our National Silicone product line saw the most movement with our solid silicone production times increasing 10 days, while our silicone foam production went up 5 days. GCP sourced hoses also rose 5 days, but fortunately all other expected production times remain unchanged from April, which is good news.
Going forward U.S. ports are bracing for another surge in supply-chain backlogs. There’s been a lull in trade flows since China has locked down major trade hub cities, including Shanghai and Shenzhen. With the decline in volumes, ocean freight rates have dropped slightly (5%) over recent weeks. However, once covid restrictions are lifted we expect this will be followed by a surge in pent up demand, which could translate to higher rates and slower delivery times. Currently there are over 475 bulk cargo and container ships waiting at Shanghai’s combined anchorage with Ningbo.
Molded Parts
With respect to our molded parts, this is the ninth month in a row in which we did not publish a production number. We continue to experience a wide variation of times depending on the style needed. If you are looking to submit an order for our molded parts please contact us to find out the appropriate lead times.
May Production Times
Our May 2022 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container. However, it excludes ocean shipping and other transit times.
If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.
Premlene
– Sheet Rubber: 70-75 Days
– Eng. Structures: 70-75 Days
National Silicone
– Solid: 65-70 Days
– Sponge: 45-50 Days
– Foam: 60-65 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Hose: 80-85 Days
– Molded Parts: Contact Us
– Clamps/Fittings: 85-90 Days
– UHMW-PE Sheet: 65-70 Days
Premlene
– Sheet Rubber: 70-75 Days
– Eng. Structures: 70-75 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 45-50 Days
– Foam: 65-70 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Hose: 80-85 Days
– Molded Parts: Contact Us
– Clamps/Fittings: 80-85 Days
– UHMW-PE Sheet: 65-70 Days