October 2023 Production Times

Conveyor Belt
Conveyor Belt

Production times have remained unchanged, with an average production time of 50.3 days across all our product lines. Notably, the Premlene Engineered Structures line reduced its production time by 5 days, while the National Silicone Foam lines extended theirs by 5 days. All other product lines remained the same.

Despite the challenges faced, it’s encouraging to note that China’s factory activity expanded for the first time in six months in September, as reported by Reuters. This signifies a positive shift and signs of stabilization in the Chinese economy. While our production numbers have remained stable leading into October, this news suggests a potentially brighter outlook for reduced manufacturing times going forward.

 

GCP Sourced Hose

Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.

 

October Production Times

Our October 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container. However, it excludes ocean shipping and other transit times.

If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.

 

October 2023 Production Times:
Premlene
– Sheet Rubber:  40-45 Days
– Eng. Structures: 55-60 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 40-45 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Molded Parts: 55-60 Days
– Clamps/Fittings: 55-60  Days
– UHMW-PE Sheet: 50-55 Days
September 2023 Production Times:
Premlene
– Sheet Rubber:  40-45 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 35-40 Days
– Sponge: -30-35 Days
– Foam: 35-40 Days
Rubatex
– Sponge: 70-75 Days
GCP Sourced
– Molded Parts: 55-60 Days
– Clamps/Fittings: 55-60  Days
– UHMW-PE Sheet: 50-55 Days