May 2024 Production Times

Factory making rubber conveyor belts with black rubber rolls

May 2024 Production Times

This month, our overall production times have remained stable, with the average production duration holding steady at 56.5 days, consistent with last month. Despite this overall stability, there have been changes within specific product lines. The production time for our Premlene Sheet Rubber and Engineered Structures line has increased by 5 days, while our National Silicone Foam and GCP Sourced UHMW-PE line has decreased by the same amount. Production times for all other product lines have remained unchanged.

The manufacturing landscape in China is showing signs of improvement as restrictions are gradually eased and supply chains begin to stabilize. This positive shift is likely bolstered by the resumption of operations at key industrial facilities and ports, which is enhancing production capabilities and export efficiency. Moreover, there’s a growing adaptation among businesses to the new economic conditions, which is fostering innovation and resilience across various sectors.

 

GCP Sourced Hose

Regarding our hose line, we have not released a production number due to the temporary unavailability of an accurate production schedule. If you intend to place an order for our hose line, please contact us to find out the appropriate lead times.

 

May Production Times

Our May 2023 production times measure the change in days an average order will take to produce from the time it is submitted (all facilities). This includes the time it takes to book a container, which currently stands at an average of 10.5 days. However, it excludes ocean shipping and other transit times. 

Approximate transit times (including estimated time the ship will wait at the port before it is unloaded) are:
East Coast: 35-45 days
West Coast: 20-30 days

If you have any concerns with your orders on hand or would like to discuss anything in more detail please do not hesitate to contact us for additional support.

 

May 2024 Production Times:
Premlene
– Sheet Rubber:  55-60 Days
– Eng. Structures: 60-65 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 35-40 Days
– Foam: 40-45 Days
Rubatex
– Sponge: 65-70 Days
GCP Sourced
– Molded Parts: 65-70 Days
– Clamps/Fittings: 60-65  Days
– UHMW-PE Sheet: 55-60 Days
April 2024 Production Times:
Premlene
– Sheet Rubber:  50-55 Days
– Eng. Structures: 55-60 Days
National Silicone
– Solid: 55-60 Days
– Sponge: 35-40 Days
– Foam: 45-50 Days
Rubatex
– Sponge: 65-70 Days
GCP Sourced
– Molded Parts: 65-70 Days
– Clamps/Fittings: 60-65  Days
– UHMW-PE Sheet: 60-65 Days