October 2019 Production Notes

Sheet of EPDM black rubber on rollers lying flat - GCP Industrial Products

October 2019 Production Notes

The September production times have continued to stay positive. GCP Clamps/Fittings is the only product that shows a slight increase in manufacturing times. As for Premlene, National Silicone, Ceramic Tile, Conveyor Belt, Engineered Structures, Hose, and UHMW-PE sheeting, the production times stay the same. 

October 2019 – Current Times

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 60-65 Day

National Silicone: 30-35 Day

GCP Ceramic Tile: 35-40 Days

GCP Conveyor Belt: 60-65 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 55-60 Days

GCP UHMW-PE Sheet: 65-70 Days

Rubatex Sponge:
Times Currently Unavailable

September 2019 – Last Month

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 60-65 Day

National Silicone: 30-35 Day

GCP Ceramic Tile: 35-40 Days

GCP Conveyor Belt: 60-65 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 50-55 Days

GCP UHMW-PE Sheet: 65-70 Days

Rubatex Sponge:
Times Currently Unavailable