October 2020 Production Times

Black rubber being produced on machinery - GCP Industrial Products

October 2020 Production Times

October’s production numbers show a slight increase of times for GCP Clamps/Fittings and National Silicone Solid.  Premlene Eng. Structures production times decrease by 5 days, while Premlene Sheet Rubber, National Silicone Sponge, GCP Hose, and GCP UHMW-PE Sheet continue to stay the same. 

October 2020 – Current Times

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 50-55 Days

National Silicone Solid: 40-45 Days

National Silicone Sponge: 25-30 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 65-70 Days

GCP UHMW-PE Sheet: 60-65 Days

September 2020 – Last Month

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 55-60 Days

National Silicone Solid: 35-40 Days

National Silicone Sponge: 25-30 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 55-60 Days

GCP UHMW-PE Sheet: 60-65 Days