September 2019 Production Notes

Black rubber matting being produced on machine - GCP Industrial Products

September 2019 Production Notes

The news has continued to stay positive through August regarding our updated production times. National Silicone shows shorter manufacturing times while manufacturing times for Premlene, Ceramic Tile, Conveyor Belt, Engineered Structures, Hose, Clamps/Fittings, and UHMW-PE sheeting, stay the same. 

September 2019 – Current Times

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 60-65 Day

National Silicone: 30-35 Day

GCP Ceramic Tile: 35-40 Days

GCP Conveyor Belt: 60-65 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 50-55 Days

GCP UHMW-PE Sheet: 65-70 Days

Rubatex Sponge:
Times Currently Unavailable

August 2019 – Last Month

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 60-65 Day

National Silicone: 35-40 Day

GCP Ceramic Tile: 35-40 Days

GCP Conveyor Belt: 60-65 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 50-55 Days

GCP UHMW-PE Sheet: 65-70 Days

Rubatex Sponge:
Times Currently Unavailable