September 2020 Production Times

September 2020 Production Times

September’s production times continue to stay positive and consistent. Premlene Sheet Rubber and National Silicone Sponge are the only two materials that show a slight increase in times. Premlene Eng. Structures, National Silicone Solid, GCP Hose, GCP Clamps/Fittings, and GCP UHMW-PE Sheet continue to stay the same. 

September 2020 – Current Times

Premlene Sheet Rubber: 40-45 Days

Premlene Eng. Structures: 55-60 Days

National Silicone Solid: 35-40 Days

National Silicone Sponge: 25-30 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 55-60 Days

GCP UHMW-PE Sheet: 60-65 Days

August 2020 – Last Month

Premlene Sheet Rubber: 35-40 Days

Premlene Eng. Structures: 55-60 Days

National Silicone Solid: 35-40 Days

National Silicone Sponge: 20-25 Days

GCP Hose: 50-55 Days

GCP Clamps/Fittings: 55-60 Days

GCP UHMW-PE Sheet: 60-65 Days